Job Costing Examples: Calculate Labour Costs for an NZ Trade Job
Job costing means adding up what a specific job costs you: labour, materials and a share of overheads. You then compare that total with the price you charged. The basic formula is short. The accuracy comes from the inputs, especially the hours.
This article works through one example from start to finish. Every figure is hypothetical, in New Zealand dollars and exclusive of GST. Swap in your own numbers to reproduce the calculation.

The job costing formula
Total job cost = direct labour + direct materials + allocated overhead
- Direct labour = hours worked on the job × loaded labour rate
- Direct materials = materials and other costs bought for the job
- Allocated overhead = the job’s share of costs that cannot be traced to one job
Profit is the price minus the total job cost.
Job costing is not the same as budgeting. A budget is the plan before work starts. Job costing measures what happened. For more on that distinction, see job costing vs budgeting.
The example: a hypothetical deck build
A small Auckland building firm, which we will call Harbour Decks, quotes a fixed price to build a timber deck for a homeowner. The firm employs four builders. It estimates the job will take 64 labour hours and $6,200 of materials.
Harbour Decks is invented for this example. So are all the rates and costs below.
Step 1: Work out a loaded labour rate
A builder’s hourly wage is not what an hour of their time costs the business. The loaded rate adds employment costs and allows for paid time when no work is done.
Annual employment cost for one builder
| Item | Item | Annual cost |
|---|---|---|
| Wages | 40 hours × 52 weeks = 2,080 paid hours at $38.00 | $79,040.00 |
| Employer KiwiSaver contribution | 3.5% of wages | $2,766.40 |
| ACC levies and other employment costs | ACC levies and other employment costs Assumed allowance $1,500.00 | $1,500.00 |
| Total | $83,306.40 |
Hours actually available for work
| Item | Hours |
|---|---|
| Paid hours in the year | 2,080 |
| Less annual holidays (4 weeks) | −160 |
| Less public holidays (12 days assumed to fall on working days) | −96 |
| Less public holidays (12 days assumed to fall on working days) | −40 |
| Hours available | 1,784 |
The loaded rate
$83,306.40 ÷ 1,784 hours = $46.70 per hour (rounded from $46.696)
So each hour this builder spends on a job costs the business about $46.70, not $38.00.
The assumptions behind that rate
- The 3.5% employer KiwiSaver contribution is the default rate from 1 April 2026. Your cost differs if an employee is not a member or contributes at another rate.
- ACC levies vary by industry and earnings. Use your own figures.
- Sick leave taken varies by person and year.
- One rate is used for the whole crew to keep the example simple. In practice, calculate a rate for each pay level, or a weighted average.
- Travel, training and other non-job time are not in this rate. They are handled as overhead in Step 3.
Step 2: Add direct materials
Materials are the timber, fixings, concrete and anything else bought for this job, at the price you paid excluding GST. Include delivery and hire costs that relate only to this job.
Estimated materials: $6,200.00
Get Started Today
Upgrade your workforce management with CleverTime’s Systems Solutions
Step 3: Allocate overheads once
Overheads are costs you cannot trace to a single job: vehicles, insurance, rent, software, office wages and time that cannot be charged to any job.
A common method is an overhead rate per labour hour.
- Annual overheads (assumed): $96,000
- Expected job hours for the year (assumed): 4 builders × 1,600 hours = 6,400 hours
- Overhead rate: $96,000 ÷ 6,400 = $15.00 per job hour
Each builder has 1,784 hours available but only 1,600 expected on jobs. The other 184 hours are non-job time, and their cost is included in the $96,000.
Avoid counting overheads twice
Each cost belongs in one place only.
- Employment costs such as KiwiSaver and leave are in the loaded labour rate. Keep them out of overheads.
- Non-job time is in overheads here. Do not also spread it into the labour rate.
- Materials charged to a job are direct costs. Keep them out of overheads.
If a cost appears in two places, your job costs will be overstated and your quotes may become uncompetitive.
Step 4: Build the estimate and set the price
| Cost | Calculation | Calculation |
|---|---|---|
| Direct labour | 64 hours × $46.70 | $2,988.80 |
| Direct materials | $6,200.00 | |
| Allocated overhead | 64 hours × $15.00 | $960.00 |
| Total estimated cost | $10,148.80 |
Harbour Decks wants a 20% profit margin.
Margin versus markup
These are often confused, and the difference affects your price.
- Margin is profit as a percentage of the price.
- Markup is profit as a percentage of cost.
For a 20% margin: price = cost ÷ (1 − 0.20) = $10,148.80 ÷ 0.80 = $12,686.00
The expected profit is $12,686.00 − $10,148.80 = $2,537.20. That is 20% of the price, but 25% of the cost. A 20% margin is therefore the same as a 25% markup.
If Harbour Decks had added a 20% markup instead, the price would be $10,148.80 × 1.20 = $12,178.56, and the margin only 16.7%.
Step 5: Compare estimated and actual costs
The job takes longer than planned. Old footings have to be removed, and extra timber is needed. The crew records 74 hours, and materials come to $6,450.
| Cost | Estimate | Actual | Variance |
|---|---|---|---|
| Labour hours | 64 | 74 | +10 |
| Direct labour | $2,988.80 | $3,455.80 | +$467.00 |
| Direct materials | $6,200.00 | $6,450.00 | +$250.00 |
| Allocated overhead | $960.00 | $1,110.00 | +$150.00 |
| Total cost | $10,148.80 | $11,015.80 | +$867.00 |
| Price (fixed) | $12,686.00 | $12,686.00 | — |
| Profit | $2,537.20 | $1,670.20 | −$867.00 |
| Margin | 20.0% | 13.2% | −6.8 points |
The job takes longer than planned. Old footings have to be removed, and extra timber is needed. The crew records 74 hours, and materials come to $6,450.
Why accurate time records matter
Labour hours drive two of the three cost lines in this example: direct labour and allocated overhead. If hours are estimated from memory at the end of the week, both figures are unreliable.
Suppose the crew had written down 68 hours instead of the 74 they worked. The job would appear to cost $370.20 less than it did, and the same underestimate would carry into the next quote.
Recording time against the job as it happens removes that guesswork. CleverTime’s job costing software tracks the cost of labour against a job, project or client, with employees logging jobs as they clock in and out. It supports up to three levels of jobs, tasks and activities, so hours can be separated into stages such as demolition, framing and decking.
That gives you the actual hours for the calculation above. Your overhead rate and target margin remain business decisions, usually set with your accountant.
For a wider view of labour tracking on building sites, read construction labour cost tracking.
Use the example with your own numbers
- Calculate a loaded labour rate for each pay level.
- List your annual overheads and divide by expected job hours.
- Check no cost sits in both the labour rate and overheads.
- Estimate hours and materials for the job.
- Decide whether you are working in margin or markup, and price accordingly.
- Record actual hours and materials against the job.
- Compare estimate with actual, and note the reason for each variance.
Frequently asked questions
What is the formula for job costing?
Total job cost = direct labour + direct materials + allocated overhead. Direct labour is the hours worked on the job multiplied by a loaded labour rate.
What is a loaded labour rate?
It is the full hourly cost of an employee to the business. It includes wages plus employment costs such as employer KiwiSaver contributions and ACC levies, spread over the hours the person is actually available to work.
Should GST be included in job costs?
If your business is GST-registered, cost and price jobs exclusive of GST, then add GST to the invoice. Check with your accountant if you are unsure of your position.
What is the difference between margin and markup?
Margin is profit divided by price. Markup is profit divided by cost. A 25% markup gives a 20% margin.
How often should I compare estimated and actual costs?
At least when each job finishes. On longer jobs, checking at each stage lets you respond while there is still time to adjust.